1-A ____ is a set of activities which are networked in an order and aimed towards achieving the goals of a project.

(A) Project

(B) Process

(C) Project management

(D) Project cycle

 

2-Resources refers to

(A) Manpower

(B) Machinery

(C) Materials

(D) All of the above

 

3-Developing a technology is an example of

(A) Process

(B) Project

(C) Scope

(D) All of the above

 

4-The project life cycle consists of

(A) Understanding the scope of the project

(B) Objectives of the project

(C) Formulation and planning various activities

(D) All of the above

 

5-Following is(are) the responsibility(ies) of the project manager.

(A) Budgeting and cost control

(B) Allocating resources

(C) Tracking project expenditure

(D) All of the above

 

6-Following are the phases of Project Management Life Cycle. Arrange them in correct order

  1. Design, 2. Marketing, 3. Analysis and evaluation, 4. Inspection, testing and delivery

(A) 3-2-1-4

(B) 1-2-3-4

(C) 2-3-1-4

(D) 4-3-2-1

 

7-Design phase consist of

(A) Input received

(B) Output received

(C) Both (A) and (B)

(D) None of the above

 

8-Project performance consists of

(A) Time

(B) Cost

(C) Quality

(D) All of the above

 

9-Five dimensions that must be managed on a project

(A) Constraint, Quality, Cost, Schedule, Staff

(B) Features, Quality, Cost, Schedule, Staff

(C) Features, priority, Cost, Schedule, Staff

(D) Features, Quality, Cost, Schedule, customer

 

10-Resorce requirement in project becomes constant while the project is in its _____ progress stage.

(A) 40 to 55%

(B) 55 to 70%

(C) 70 to 80%

(D) 80 to 95%

 

ANSWERS:

1-(A), 2-(D), 3-(B), 4-(D), 5-(D), 6-(A), 7-(C), 8-(D), 9-(B), 10-(D)