Multiple Choice Questions on Project Life Cycle
Multiple Choice Questions on Project Life Cycle. Objective type questions with answers on Project Management. MCQ on Project Life Cycle.
1- A ___ is a task with a known end point.
(A) management
(B) project
(C) development
(D) all of the above
2- Which of the following is (are) project(s)?
(A) building a new house
(B) creating a new computer software
(C) launching a new product for a business
(D) all of the above
3- The successful project management is all about
(A) structure
(B) control
(C) continuously driving action
(D) all of the above
4- A deliverable is a ___ as a result of a project that is intended to be delivered to a customer.
(A) tangible good
(B) intangible good
(C) service produced
(D) any of the above
5- Each project phase is marked by completion of one or more ___ .
(A) deliverables
(B) input
(C) both (A) and (B)
(D) none of the above
6- ___ projects often interact with other projects in terms of the functional departments.
(A) big
(B) Simultaneous
(C) small
(D) none of the above
7- Which of the following is a non-project?
(A) production of weekly employment reports
(B) The use of a manufacturing line to produce a flow of standard products
(C) the delivery of mail
(D) all of the above
8- Projects compete with functional departments for ___ .
(A) resources
(B) personnel
(C) resources and personnel
(D) none of the above
9- The extended Project life cycle adds two more phases to the sequence, which are
(A) concept and operations
(B) operations and termination
(C) handover and operations
(D) implementation and operations
10- Which of the following is true for Project Management?
(A) It is a formal discipline for managing projects
(B) There is no single life cycle that applies to all projects
(C) Every project has some elements that are unique
(D) All of the above
ANSWERS:
1-(B), 2-(D), 3-(D), 4-(D), 5-(A), 6-(B), 7-(D), 8-(C), 9-(B), 10-(D)